PWC’s Proposed Route 234-Brentsville Road Interchange (a grade-separated interchange with continuous green-T intersections).  To see the details, view the design display boards from the December 8 public hearing.

March 18, 2022 Update:  The County has posted this followup video presentation on the proposed project design, and a virtual followup public meeting is scheduled for March 22 at 6 pm.

Several of our concerns with this project are currently being addressed (although the trail bridge over Rte 234 just east of the interchange is merely being “studied” at present).

However, all trail connections to and from Rte 234 Business and the long-planned future trail along Route 234 North would still require a two-step at-grade crossing of 12 signalized traffic lanes at the rebuilt intersection of Bradley Cemetery Way and Rte 234 Business, and two of the original six at-grade trail crossings of free-flowing highway ramps would remain.  Those remaining design flaws would still create considerable delays and hazards for trail users.


Active Prince William submitted the following public comments to the Prince William County Department of Transportation in response to its December 8, 2021 Design Public Hearing on its proposed Interchange at Route 234 and Brentsville Road.  The public comment period closed on December 18, 2021.


The advertised design of the above-referenced project does not safely and effectively accommodate people bicycling, walking, or using other active transportation modes through the project area.  The design of the advertised non-motorized connections should be revised substantially to provide reasonable access and safety for people who are not traveling inside motor vehicles.

1) The Proposed Design Includes Too Many Dangerous At-Grade Trail Crossings of Free-Flowing, High-Speed Highway Ramps

This interchange is the connection point for Prince William County’s two major east-west cross-county shared-use paths; namely, the asphalt sidepaths along Route 294 (Prince William Parkway) and Route 234 South (Dumfries Road).  While the proposed design does include a circuitous shared-use path, meandering through the center of the interchange, that links both major paths, this advertised path connection would require people walking or bicycling to cross five separate at-grade crossings of high-speed highway ramps without any protection from traffic signals.  This tortuous path connection is not merely long, indirect, slow, and tedious; it is extremely hazardous and will both significantly deter trail use and lead to multiple pedestrian and bicycling injury crashes and eventually to traffic deaths.

Four of the six at-grade trail crossings of free-flowing, high-speed highway ramps that are included in the advertised design

Since this proposed interchange would create near-Interstate-highway-quality, free-flow connections for motor vehicles from all five approaches, it is unconscionable to have any at-grade trail-roadway crossings in this project. 

Rather than connect the two existing major trails via five at-grade highway ramp crossings within the center of the interchange, bicyclists and pedestrians should instead be routed near the eastern and northern perimeters of this interchange via pedestrian/bicycle overpasses of three legs of this intersection; namely, Route 234 South, Route 294, and Route 234 Business.   While all three pedestrian/bicycle overpasses proposed below are clearly warranted for safe and equitable access, they are listed above in priority order.

With that said, the trail approaches to many of the proposed at-grade roadway crossings in the present design are often very short and nearly parallel to the crossed roadway, especially at most of the four at-grade roadway crossings near the intersection of Bradley Cemetery Way and Route 294.  With such closely spaced crosswalks and sharply bent trail approaches, a bicycle rider would need to fully stop well before reaching the crosswalk, dismount, and manually reposition her bicycle to clearly view the approaching cross-traffic, and she will thus require much larger gaps in traffic to safely cross each roadway ramp.  The clustering of some of these crosswalks and the resulting short path segments between them would also likely create conflicts and collisions with any trail users approaching from the opposite direction.  If the final design retains any at-grade roadway crossings, the trail approaches should be as perpendicular to each crossed roadway (or in direct line with each crosswalk) as possible and substantially longer than the crosswalk itself.

The advertised design includes four closely spaced at-grade path crossings of free-flowing highway ramps near Route 294

The proposed shared-use path junction for the sidepath along Brentsville Road, near the southern end of the intersection, is also poorly designed.  The approach of the Brentsville Road sidepath to the Ramp C crossing is far too close and nearly parallel, not perpendicular, to Ramp C.  In addition, the Brentsville Road sidepath joins the longer path leading to Route 234 South at a sharp 90-degree angle, rather than making gentle Y-shaped connections much farther east of Ramp C.  The latter design flaw is replicated at the path junction near Bradley Cemetery Way and Route 234 Business.  Published AASHTO and VDOT guidance describe how to design appropriate path connections for people riding bicycles at 15 to 20 MPH.

The sidepath along Brentsville Road is poorly designed at its northern end near the Ramp C crossing.

 

2) Separating Shared-Use Paths from High-Speed, Free-Flowing Vehicle Traffic is a Long-Standing Practice in Northern Virginia

The practice of designing and building high-quality shared-use paths along and/or across limited-access highways without any at-grade road crossings has at least a 40-year history in Northern Virginia.  When the Virginia Department of Transportation designed and built I-66 in Arlington circa 1980, it established a continuous 10-foot asphalt path immediately adjacent to that highway with zero at-grade roadway crossings for the more than four miles between N Scott St in Rosslyn and the City of Falls Church at N Van Buren St and Route 29.

The 45-mile Washington & Old Dominion (W&OD) Trail, which runs from Shirlington to Purcellville, is Northern Virginia’s preeminent active transportation and recreation facility, largely because it has zero at-grade crossings of fast or busy roadways that are not protected with traffic signals.

In Arlington, the W&OD Trail benefits from both local roadway overpasses of the adjacent I-66 to cross under N. Ohio St and N. Patrick Henry Dr and stream underpasses for the adjacent Four Mile Run to cross under N. Sycamore St, N. Wilson Blvd, N. Carlin Springs Rd, and Arlington Blvd.  As a result, the W&OD Trail has zero at-grade roadway crossings for the nearly four miles between Columbia Pike and the Falls Church line at N Van Buren St.

For at least the past 30 years, NOVA Parks (formerly NVRPA) has required all builders of new or widened roads across its W&OD Trail to include a grade-separated crossing for the trail.  As a result, the W&OD Trail west of Four Mile Run now includes more than two dozen separate trail overpasses or underpasses at Route 29 in East Falls Church, Route 7 in Falls Church, I-495, American Dream Way, Reston Parkway, Town Center Parkway, Fairfax County Parkway, Herndon Parkway East, Center St in Herndon, Herndon Parkway West, Church Road, Atlantic Blvd, Route 28/Sully Road, Pacific Blvd, Loudoun County Parkway, Ashburn Village Blvd, Claiborne Parkway, Belmont Ridge Road, Battlefield Parkway SE, Route 15, Plaza St SE, Route 7/Harry Bryd Hwy, the Route 9/Route 7 Interchange, and the Route 287/Route 7 Interchange.  Many of those grade-separated roadways have lower traffic speeds and/or volumes than Routes 234 and 294.

Currently, the I-66 Outside the Beltway Express Lanes Project is in the process of building 11 miles of shared-use paths adjacent to I-66 in Fairfax County, as well as safe bicycle and pedestrian facilities on nearly all of the roads that cross I-66.  These new bicycle and pedestrian connections have been carefully and creatively designed to avoid at-grade roadway crossings, especially crossings with free-flowing, high-speed traffic.

Operated by the National Park Service’s George Washington Memorial Parkway unit, the 18-mile Mount Vernon Trail between Rosslyn and the Mount Vernon Estate is another premier shared-use path in Northern Virgina.  Because it follows the Potomac River, the Mount Vernon Trail has always had few at-grade road crossings.  Nevertheless, many millions of dollars have been invested over the years to remove busy at-grade highway ramp crossings near Reagan National Airport, and—with no highway ramp interruptions—to connect the Mount Vernon Trail to Rosslyn, the Pentagon, and Crystal City and to cross the Potomac River on the Woodrow Wilson Bridge.

In recent years, the Virginia Department of Transportation has been building a network of pedestrian and bicycle overpasses of I-495 and the Dulles Toll Road in the Tysons area, including along Route 7 across the Dulles Toll Road, Trap Road over the Dulles Toll Road in Vienna,  the Jones Branch Connector over I-495 south of the Dulles Toll Road in McLean, and the Tysons One/Old Meadow Road overpass of I-495 near Pimmit Hills.

Bicycling and walking are viable transportation and very popular recreation modes in communities with high-qualify shared use paths, and the absence of at-grade highway ramp crossings is a key contributor to the safety, use, and enjoyment of those paths.  Prince William County will never create the types of high-quality paved trails enjoyed in most other Northern Virginia localities if it continues to build shared-use paths with hazardous at-grade crossings of highway ramps.

 

3) Install a Pedestrian/Bicycle Bridge over Route 234 on the East/South Side of the Interchange to Create a Safe and Direct Connection between the Route 234 and Route 294 Paths

The Route 234 and Route 294 sidepaths–the two major existing bike/ped facilities within the project area—could be linked very safely and directly by building a pedestrian/bicycle bridge between these two trails on the east/south side of the interchange in the vicinity of the Meadows Farms Garden Center.  Because the elevation on the south side of Route 234 is considerably higher than the roadway, no long bridge approach should be needed on that side of the overpass.

Our proposed direct connection of the existing Route 294 and Route 234 shared-use paths via a pedestrian/bicycle overpass of Route 234 on the east side of the interchange near the Meadows Farms Garden Center

 

4) Incorporate Safe and Direct Connections to and from Route 234 Business (Dumfries Road) and the Planned Trail along Route 234 North

Even if the direct pedestrian/bicycle bridge requested above is built, safe and efficient bicycling and walking connections would still be needed to and from all five legs of this interchange; namely Route 294 (Prince William Parkway), Route 234 South (Dumfries Road), Route 234 North (Prince William Parkway), Brentsville Road (Route 649), and Route 234 Business (Dumfries Road).

Although the current Prince William County Comprehensive Plan calls for building a major shared-use path along Route 234 North, the current project design does not depict this future trail or its connections to the four other legs of this interchange.  The current design should be modified to identify the right-of-way and connections for the future Route 234 North shared-use path within the project limits.

Presently, Route 234 Business (Dumfries Road) provides bicycle and pedestrian access to the project area from most of the City of Manassas, the Bradley Square development, and the Godwin Drive corridor.  Bicyclists and pedestrians now readily use Route 234 Business to access Brentsville Rd, the Route 234 South sidepath, and the Route 294 sidepath via the roadways and crosswalks at the two nearby existing Route 234 intersections (and alternatively via Bradley Cemetery Way if desired).

The proposed design, however, would severely degrade this walking and bicycling access to and from Route 234 Business by expanding the limited-access control perimeter and by creating a large new signalized intersection at Route 234 Business and Bradley Cemetery Way.  To access any other leg of the interchange, bicyclists and pedestrians from Route 234 Business (and also the future shared-use path along Route 234 North) would apparently need to 1) cross two separate legs of a large, signalized Route 234 Business/Bradley Cemetery Way intersection—spanning a total of 12 vehicle lanes—2) cross a free-flowing lane of right-turning traffic from northbound Brentsville Road, and 3) finally cross either one or four-additional high-speed highway ramps within the center of the interchange, depending upon one’s destination.  This proposed pedestrian and bicycle access is neither safe nor effective and is a significant degradation of the existing conditions.

The advertised design would require at least a four-stage maneuver for pedestrians and bicyclists using Route 234 Business (or the future shared-use path along Route 234 North) to access any other leg of this interchange: 1) cross five lanes of stopped traffic at Route 234 Business, 2) cross seven lanes of stopped traffic at Bradley Cemetery Way, 3) cross one-lane of free-flowing right-turning traffic from northbound Brentsville Road, and 4) cross either one or four additional highway ramps—located elsewhere inside the interchange–with free-flowing, high-speed traffic, depending upon one’s final destination.

The current design should be modified to add an elevated trail on a berm along the north side of Bradley Cemetery Way, with pedestrian/bicycle bridges over both Route 234 Business and Route 294.  Such an elevated trail would connect the existing Route 294 path with the west side of Route 234 Business and the long-planned future trail along Route 234 North.  Placing this trail connection on a berm along the north side of Bradley Cemetery Way should lower construction costs and improve walking and bicycling conditions by minimizing grade changes along this trail connector between the pedestrian bridges over Route 294 and Route 234 Business.  Integrating these safe and direct grade-separated trail connections as part of the current project should provide them at far lower cost than if constructed later as one or more standalone projects.

Rough alignment of our proposed grade-separated trail connections along the northern perimeter of the interchange, with two relatively short pedestrian/bicycle overpasses of Route 234 Business on the west (connected to future shared-use paths along Route 234 Business and Route 234 North) and Route 294 on the east (connected to the existing Route 294 shared-use path).  Between Route 234 Business and Route 294, the connecting path could be built on a berm along the north side of Bradley Cemetery Way.

 

5) Reduce Interchange Construction Costs by Eliminating Unnecessary Trail and Roadway Features

To offset the cost of adding up to three pedestrian/bicycle bridges, the current design could be modified to eliminate unnecessary features.

If all three pedestrian/bicycle bridges recommended above are built over the eastern and northern edges of this interchange, all currently designed pedestrian/bicycle infrastructure within the center of this interchange would be unnecessary and could be eliminated, including the currently proposed 14-foot-wide shared-use path on the western interchange bridge.

The cost of the western interchange bridge should be further reduced by eliminating the advertised continuous green-T intersection at the exit ramp from southbound Route 234 and by eliminating one of the two northbound travel lanes from Brentsville Road on the western interchange bridge.  Traffic volumes on Brentsville Road, which had an AADT of only 2800 in 2019, will never warrant two northbound lanes through this interchange.  Eliminating one unnecessary travel lane (and potentially also the shared-use path) would reduce the cost of this roadway bridge considerably.  A traffic signal, stop sign, or a roundabout could replace the proposed continuous green-T intersection.

 

To reduce project costs, one northbound lane from Brentsville Road could be eliminated on the western overpass.  This second northbound lane is not warranted by current or future Brentsville Road traffic volumes and was only designed to accommodate an unnecessary continuous green-T intersection for traffic exiting southbound Route 234.  If the advertised design is modified to add all three pedestrian/bicycle overpasses recommended above, the 14-foot wide shared-use path could also be eliminated from this overpass.  The width of the advertised western overpass could thus be reduced 39%, from 67 feet to 41 feet.

Reducing northbound Brentsville Road to a single lane though the interchange would also reduce the widths of the roadway north of the western overpass and the width of the signalized intersection of Brentsville Rd/Route 234 Business at Bradley Cemetery Way.

The Route 234 Business/Dumfries Road roadway is already needlessly wide south of Godwin Drive.  According to VDOT’s 2019 traffic count data, this roadway segment has an AADT of only 8600.  Presently, the Route 234 Business roadway south of Godwin Drive is five lanes wide, whereas only three lanes of roadway (one travel lane per direction plus space for a left-turn lane in the center) would adequately accommodate a future doubling of this Route 234 Business Traffic (i.e., to an AADT of 17,200).

Rebuilding Route 234 Business between Godwin Drive and Bradley Cemetery Way as a three-lane roadway, instead of as a five-lane roadway, would allow the addition of both a shared-use path and a sidewalk within the existing right-of-way along this key road segment.  Moreover, the shared-use path (and not the sidewalk) should be located along the west side of Route 234 Business to align with the west-side path just built within the City of Manassas between Hastings Drive and Donner Drive.

Thank you for considering these comments.  We look forward to seeing a substantially modified final design for the shared-use path connections that will eliminate all at-grade roadway crossings and accommodate safe and reasonably direct pedestrian and bicycle access to and from all five legs of this key interchange.


On December 27, 2021, we submitted the following additional comment:

Building 12-foot-wide travel and turn lanes on Brentsville Road, Route 234 Business, and Bradley Cemetery Way is clearly excessive, since 11-foot-wide lanes are more than adequate for those local, lower-speed roadways.  Designing 11-foot travel lanes on the Brentsville Road bridge over Route 234 would further lower the cost of building that overpass.  With 8-foot-wide paved shoulders included on that overpass, 12-foot-wide travel lanes are most definitely wider than needed.

A narrower Route 234 Business on the north side of Bradley Cemetery Way would also reduce the cost of a pedestrian and bicycle overpass at that location and would shorten pedestrian crossing times if at-grade crosswalks are still included at Route 234 Business and/or Bradley Cemetery Way in the final design.

###

Active Prince William’s Initial Comments on the Proposed Design of the Route 234-Brentsville Road Interchange

 
PROBLEM:
Forcing bicycle and pedestrian users to cross FOUR separate free-flowing, high-speed vehicle lanes is an unacceptable way to connect two of the major trails in the county.  The section should be removed from the design.  It is too dangerous.  [Added Note: The proposed design forces bicyclists and pedestrians to negotiate a fifth high-speed at-grade road crossing (of the ramp from northbound Brentsville Road to southbound Route 234) to actually link these two major trails.  Furthermore, to access or egress Route 234 Business/Dumfries Rd, bicyclists and pedestrians would be forced to negotiate a sixth high-speed at-grade road crossing plus 12 vehicle lanes at two controlled intersection legs at Bradley Cemetery Way.]

 

RECOMMENDED SOLUTION:
Add an additional bike/ped bridge crossing of Route 234 south/east of the planned interchange to directly and safely connect the Route 234 Trail and the Prince William Parkway Trail.

 

HOW TO PAY FOR THIS RECOMMENDED SOLUTION:
1) Remove the proposed bike/ped infrastructure with four at-grade roadway crossings from the Bradley Cemetery Way area:

2) Change the Continuous Green-T Intersection at Brentsville Road and the off-ramp from VA234 Bypass South to a Roundabout, Standard Two-Phase Traffic Light or a Three-Way Stop Sign.  Future traffic volumes do not warrant the expensive infrastructure needed for a Continuous Green-T Intersection.

3)  Remove one northbound lane from the planned Brentsville Road Bridge to create a smaller/cheaper bridge footprint.  Future traffic volumes do not warrant having two northbound vehicle lanes on this bridge.

Environmental and Social Injustice in Prince William County–In 2021. Yes, 2021.

Proposed Route 28 Bypass Alignment (as of February 2021)

Remember the bad old days, when government officials routed new highways through minority neighborhoods and displaced low-wealth families for the benefit of more-wealthy White drivers?

Well, it’s happening right now in Prince William County.

To construct the Route 28 Bypass/Godwin Drive Extended, County supervisors would tear down more than 50 homes in a low-income and heavily Hispanic neighborhood.  At least three families in the Bull Run Mobile Home Park would have to move.  The entire mobile home park could close and be replaced by a mixed-use development with much higher rents/mortgage payments.

The losers:  those living in a rare affordable community in Northern Virginia.  The beneficiaries:  commuters from Fauquier, Culpeper, Stafford, and beyond driving to high-paying jobs in Fairfax and DC.

Racial Characteristics of Census Tracks Surrounding the Route 28 Bypass Alignment (pink line).

Building the Route 28 Bypass would cost at least $300 million, not counting the widening of the adjoining stretch of Godwin Drive in the City of Manassas, estimated in 2019 to cost more than $40 million.   Prince William taxpayers would provide $200 million in funding through a County bond issue.  It’s a government subsidy for exurban drive-alone commuters, few of whom would be traveling to jobs in the County or increasing the local commercial tax base.

The Route 28 Bypass would poorly serve commuters.  The Bypass would significantly worsen traffic congestion and travel times on Route 28 in Centreville,  compared to its “No-Build Alternative”, and includes no accommodations for efficient bus transit or managed lanes, such as high-occupancy vehicle (HOV) or high-occupancy toll (HOT) lanes, to reduce single-occupant vehicle (SOV) trips.

The equity issue is most relevant today.  The neighborhoods being destroyed are designated Equity Emphasis Areas.  They have been stable, affordable communities for Hispanic residents.  Carving up communities occupied by minority groups, for the benefit of those fortunate to have high-paying jobs closer to DC, is a modern version of environmental injustice.

Oh, and the commuter road would blast through Bull Run Regional Park and the Flat Branch stream valley.  If the noisy and polluting Route 28 Bypass highway barrier isn’t built, the Flat Branch stream valley could become a wonderful linear park and natural habitat that significantly enhances the livability and bike/ped connectivity of its adjacent neighborhoods.  After Prince William voters approved the road-expansion bonds in 2019, County officials cancelled an Environmental Assessment, to avoid examining alternative routes with fewer environmental and social impacts

There’s a chance to stop this environmental and social injustice.  Prince William County supervisors will approve a capital budget by June, 2022 which could include funding for the Route 28 Bypass–or they could instead allocate $200+ million in local funds over the next twenty years to other projects, such as affordable housing, and not repeat the injustices of the 1950s.

For the County’s sales job, see https://route28bypass.com.  For the rest of the story, see the Active Prince William website at https://www.activepw.org.

Active Prince William is a group of concerned citizens who advocate for better opportunities, support, and infrastructure for active mobility, better public transportation, and healthy lifestyles within Prince William County, Manassas, and Manassas Park.  We are working to help make Prince William County and Greater Manassas a more livable, healthy, equitable, and sustainable community.   Follow us at https://www.activepw.org/ , @Active_PW on Twitter, and ActivePW on Facebook.

Our Recommendations for Upcoming NVTA Transportation Funding Applications from PWC

On July 19, 2021, Active Prince William sent the following email message to the Prince William County Planning Commission, which will soon be briefed by County transportation staff on the transportation projects that the County is considering for submission to the Northern Virginia Transportation Authority (NVTA) in Fall 2021 for  potential regional funding .  Various local transportation and elected officials, including the Prince William Board of County Supervisors, were copied on this message.

 


Active Prince William supports the integration of land use, housing, and transportation planning.  Having the Transportation Department brief the Commission on planned grant applications is a start.  That step should be followed by a formal public hearing and a vote of the Planning Commission.

New mobility infrastructure should substantially enhance the transit and bike/pedestrian network, rather than simply expand the road network and add a desolate side path.  Traditional “business as usual” planning for the next decade will sabotage the county’s commitment to reduce greenhouse gas emissions by 2030 to 50% of the 2005 levels.  The transportation sector generates the greatest amount of greenhouse gas emissions in Prince William now.  The only way to meet the 2030 target is to reduce the carbon spewing from tailpipes in Prince William, and that requires a new approach to planning for multimodal *mobility* and access, rather than just paving more roads for drive-alone motorists.

In 2030, most cars will still be fueled by gasoline.  Virtually every project that paves more lane miles will increase Vehicle Miles Traveled (VMT) and greenhouse gas emissions from those cars.  To understand the impact of various proposed projects, the Planning Commission should identify the projected increase in VMT associated with each transportation project, and use that data when determining which projects to recommend to the BOCS.

The Planning Commission recommendations to the BOCS should be guided by the Strategic Plan.  The Strategic Plan calls for the County to develop in a sustainable way.  As you know, new transit and bike/pedestrian projects have the potential to reduce or minimize VMT and associated greenhouse gas emissions.  To be sustainable, the County must abandon the old school approach of just building more roads–and acknowledge that more roads have not reduced traffic congestion.

For the upcoming NVTA grant program, Active Prince William recommends submitting the following projects to the next NVTA funding round (FY26/FY27). As you can see, none of these projects’ main intent is to add lane miles.  All projects support Transit, Active Transportation, and/or Intersection/Interchange improvements.

  • Route 1/Potomac Mills BRT (TRANSIT) – NVTA 38/39
  • Dale Blvd Improvements (TRANSIT) – NVTA 241
  • VRE Second platforms – Manassas Line (TRANSIT) – NVTA 300
  • I-95 Ped/Bike Crossings (TRAILS/ACTIVE TRANSPORTATION) – NVTA 300/242/49/241
  • Balls Ford Road/I-66 Trail Improvements (TRAILS/ACTIVE TRANSPORTATION)  – NVTA 50
  • Route 123 Improvements (INTERCHANGE/INTERSECTION IMPROVEMENT) – NVTA 242
  • Wellington Rd/Sudley Manor/VA234 Interchange Improvements (INTERCHANGE/INTERSECTION IMPROVEMENT) – NVTA 222
  • Minnieville Rd/PW Parkway Interchange (INTERCHANGE/INTERSECTION IMPROVEMENT) – NVTA 279
  • Pageland Ln/Sanders Ln Safety Improvements (INTERCHANGE/INTERSECTION IMPROVEMENT) – NVTA 227
  • Route 28 STARS (INTERCHANGE/INTERSECTION IMPROVEMENT) – NVTA 29/32

Many of these projects do not match exactly with the NVTA Transaction description but the NVTA has set a precedent by funding innovative intersection improvements at University Boulevard and Prince William Parkway even though NVTA Transaction clearly requires “Construct Interchange at Prince William Parkway and University Boulevard.” (NVTA 324).  Active Prince William agrees with this approach as the intent of the projects is to improve the specified transportation segment.

Below is the list of projects that were not funded in the previous NVTA funding round (FY24-FY25).   As you can, see most of these projects’ main intent is to add lane miles that will induce new VMT and future congestion.  We need to stop advancing projects that continue to increase car dependency and have long-term adverse impacts on the climate and county budget.

  • Van Buren Road North Extension: Route 234 to Cardinal Drive (NEW ROADWAY)
  • Construct Route 28 Corridor Roadway Improvements (NEW ROADWAY/BYPASS)
  • University Boulevard Extension: Devlin Road to Wellington Road (NEW ROADWAY)
  • Wellington Road Widening: University Boulevard to Devlin Road (ROAD WIDENING)
  • Devlin Road Widening: Linton Hall Road to Relocated Balls Ford Road (ROAD WIDENING)
  • Route 234 and Sudley Manor Drive Interchange (INTERCHANGE/INTERSECTION IMPROVEMENT)
  • Prince William Parkway at Clover Hill Road Innovative Intersection (INTERCHANGE/INTERSECTION IMPROVEMENT)
  • Prince William Parkway at Old Bridge Road Intersection Improvements (INTERCHANGE/INTERSECTION IMPROVEMENT) | Funded via Smart Scale

###

APW Urges Its TPB Members to Ensure New Transportation Plans Meet Climate and Equity Goals

 

On June 15, 2021–in advance of the June 16 meeting of the National Capital Region Transportation Planning Board (TPB) at which the project submissions for updating Visualize 2045, the region’s long-range transportation plan, were scheduled for adoption –Active Prince William sent the following message to Prince William County’s two representatives on that regional transportation planning body–Prince William Board of County Supervisors Chairman Ann Wheeler and Neabsco District Supervisor Victor Angry.   We also sent similar messages to the TPB members who represent the Cities of Manassas and Manassas Park–Manassas Vice Mayor Pamela Sebesky and Manassas Park Mayor Jeanette Rishell.

Here’s a summary of the contentious June 16, 2021 TPB meeting, at which a proposal to craft a climate-friendly regional transportation plan for adoption  by 2024 was agreed to


The National Capital Region Transportation Planning Board (TPB) will be taking up a resolution at their June 16th meeting regarding a Visualize 2045 Alternative Build Scenario that would aim to achieve TPB climate and equity goals through the use of transportation demand management, transit, and land use strategies consistent with regional policy goals, a modified regional project list that reduces the number and scale of road capacity expansion projects in accordance with anticipated reduced travel demand, and with particular focus on public transportation and pedestrian/bicycle improvements needed to serve mobility disadvantaged populations.  This is being brought forward because the recently submitted project updates to Visualize 2045 will not meet the TPB climate and equity goals.

Due to the time and resource constraints at this point in the Visualize 2045 update process, Active Prince William recommends Prince William County support the following action plan to support meeting TPB climate and equity goals:

1)    Commit to completing the TPB Climate Change Mitigation Study and review it thoroughly at the regional and jurisdictional levels through the first quarter of 2022.

2)    Formally commit to assisting the TPB to develop a set of transportation policies and projects, by the end of 2022, which would be implementable at the jurisdictional and regional levels, consistent with the recommendations of the Climate Change Mitigation Study, that, when fully implemented will assure the region will meet its climate change mitigation goals

3)    Commit to take actions to officially adopt the projects and policies developed to attain the region’s climate goals within the transportation sector, and advance these projects into the region’s LRTP for a mid-term update to be completed in 2024

As voting members of the TPB, this is an opportunity for Prince William County to be a transportation planning leader as it relates to climate and equity in the region.   Supporting this initiative aligns with PWC BOCS Resolution 20-773: Regional Climate Mitigation and Resiliency Goals and the Prince William County Equity and Inclusion Policy.

The updated mobility chapter of the comprehensive plan should be aligned with this action plan.  Prince William County should also advocate these measures be included as the starting point for the next NVTA Transaction Plan.  To support this the Prince William County should advocate that the General Assembly act to modify the NVTA statute to align with your climate and equity goals.

The climate is not waiting. The time to act is now.